Construction Technology of Pile Driving Spiral Steel Pipe

Piling spiral steel pipeSSAW is a spiral seam steel pipe made of strip steel coils as raw materials,Guest Posting often extruded and formed by automatic double-wire double-sided submerged arc welding. So, what is the piling spiral tube like during construction? How is the piling spiral tube produced? The following spiral tube manufacturers will introduce to you.


1. Penetration of piling pipe

1) Before construction, the control of sample piles should be rechecked one by one according to the original design drawing and the proposed axis line, and the measurement records should be made. Piling construction can only be carried out after the recheck is correct. After the pile-driving spiral pipe pile is transported to the site, it is hoisted with one-point lashing when it is hoisted to the pile position to insert the pile, and the pile-driving spiral pipe pile is aligned with the previously released pile position to ensure that the pile croppers is accurate and vertical. Before pile driving, a special pile cap must be placed on the pile head, and a hardwood damping pad must be placed on the pile cap. Placed on the top of the pile, it will self-sink, and a large amount of penetration will penetrate into the soil. After it is settled to stability, hammering will be carried out;

2) At the beginning of piling, the piling opportunity will be driven empty due to the large penetration. When starting the hammering operation, the test driving should be slowly interrupted until the pile enters a certain depth of the ground, and continuous hammering shall not be allowed. Piling process
In the process, the verticality of the guide rod of the pile driver and the pile must be corrected at any time, and the pile hammer, pile cap and pile must be kept on the same longitudinal axis;


3) After the pile-driving spiral pipe pile is driven into 1 ~ 2m, the verticality should be re-corrected. When the pile is driven to a certain depth and the quality of the piling is good, then continue to be beaten until it is 60cm~80cm above the water surface to stop the hammering. Connect the piles and repeat the above steps until the design elevation is reached. If the pile position is found to be inclined during the construction process (>1/100L L: steel pile length), it should be adjusted in time or pulled out the steel pipe pile and re-construction;

4) The buried depth of pile driving spiral pipe pile: 10m through the riverbed, and the sinking amount within one minute of percussion does not exceed 5mm.


2. Connect the pile

The pile-driving spiral pipe pile body connection adopts the butt welding of the pile body up and down. Before welding, the deformed and damaged part of the lower pile pipe must be trimmed, and the rust, water or oil sludge sand at the end of the upper pile pipe must be removed and polished.
Make good welding joints so that the gap between the upper and lower piles is 2 ~ 4mm. At the same time, multi-layer welding is used. After each layer of welding seam is welded, the welding slag should be removed in time, and the appearance inspection should be carried out.Add welding block to strengthen the connection of the upper and lower piles. After welding, it must be cooled for more than 5 minutes before hammering and piling.

3. Welded pile cover

After the construction of the pile-driving spiral pipe pile is completed, sand is manually poured into the pile to the top of the pile, and the pile cover is welded on the upper part of the steel pipe pile, and at the same time, 8 to 12 anchor steel bars of 20 mm are welded on the outer wall.